Current Water Projects

Project

Status

Funding Source

Budget

Spent

%Remaining

Sanitary Sewer - Wastewater InterceptorDesign; Dec 2027Series 2023 - $17,065,000 Combined Tax & Revenue Certificates of Obligation$11,000,000$18,242.0999.87%
Ground Storage TankRFP under review2021 American Rescue Plan Act (ARPA)$963,919.00$48,848.41
HIllside Addition SS UpgradeUnder designSeries 2023 - $17,065,000 Combined Tax & Revenue Certificates of Obligation  $900,000.00

SCADA UpgradeIn progress



EPA Lead and Copper Rule (LCP) Compliance ProjectOngoing, Completion October 2024Series 2023 - $17,065,000 Combined Tax & Revenue Certificates of Obligation $76,093.00

North Road -400-600 Block -   waterline upgradeUnder designCDBG$472,182.50

Completed Projects

Project Status Funding Source Cost
Water Rehabilitation - 700 Block Shady Lane Completed Water/Sewer $19,825.00